Larry O'Shaughnessy architecte


 

MONTANK - NEW OFFICES, MONTREAL
5978 est, Notre-Dame, Montréal (Québec)

Construction Progress Report

These pages are dedicated to presenting a photographic report of construction progress of the above-mentioned project.

Week 05, ending September 12th, 1998

Weekly progress summary:

  • built-up roofing excluding parapets is completed on September 7, 1998

  • interior partitions are started

  • some electrical and mechanical roughing-in is initiated


Click on thumbnail image to see full-size version

98091002.jpg
98091002.jpg

26.27 Kb
98-09-25 05:07:30
98091003.jpg
98091003.jpg

33.18 Kb
98-09-25 05:09:26
98091004.jpg
98091004.jpg

31.59 Kb
98-09-25 05:11:10
98091005.jpg
98091005.jpg

30.19 Kb
98-09-25 05:11:58
98091006.jpg
98091006.jpg

30.30 Kb
98-09-25 05:12:50
98091007.jpg
98091007.jpg

28.32 Kb
98-09-25 05:18:48
98091008.jpg
98091008.jpg

36.46 Kb
98-09-25 05:17:28
98091009.jpg
98091009.jpg

28.81 Kb
98-09-25 05:25:48
98091010.jpg
98091010.jpg

25.42 Kb
98-09-25 05:24:40
98091011.jpg
98091011.jpg

29.97 Kb
98-09-25 05:23:58
98091012.jpg
98091012.jpg

22.72 Kb
98-09-25 05:21:44
98091013.jpg
98091013.jpg

21.47 Kb
98-09-25 05:20:10
payloader.jpg
payloader.jpg

24.67 Kb
98-09-25 05:04:06

Home|Previous Week (4)|Next Week (6)


Prepared by
Larry O'Shaughnessy, architect

Comments are welcome !
mail.gif (14893 bytes)
lgoshaug@total.net

© 2014, Larry O'Shaughnessy architecte.
Date de la dernière mise à jour de cette page: 2014-10-31