Larry O'Shaughnessy architecte


 

MONTANK - NEW OFFICES, MONTREAL
5978 est, Notre-Dame, Montréal (Québec)

Construction Progress Report

These pages are dedicated to presenting a photographic report of construction progress of the above-mentioned project.

Week 07, ending September 26th, 1998

Weekly progress summary:

  • Drywall board installation is completed & joint taping has begun.
  • HVAC main ductwork is essentially completed.
  • Rough plumbing and pipe insulation is essentially complete.  Systems have been tested.
  • All interior doors are hung.

Click on thumbnail image to see full-size version

98092401.jpg
98092401.jpg

26.99 Kb
98092402.jpg
98092402.jpg

23.79 Kb
98092403.jpg
98092403.jpg

22.50 Kb
98092405.jpg
98092405.jpg

20.80 Kb
98092406.jpg
98092406.jpg

25.22 Kb
98092407.jpg
98092407.jpg

30.72 Kb
98092409.jpg
98092409.jpg

20.19 Kb
 

Home|Previous Week (6)|Next Week (8)


Prepared by
Larry O'Shaughnessy, architect

Comments are welcome !
mail.gif (14893 bytes)
lgoshaug@total.net

© 2014, Larry O'Shaughnessy architecte.
Date de la dernière mise à jour de cette page: 2014-10-31