Construction Progress Report

These pages are dedicated to presenting a photographic report of construction progress of the above-mentioned project.

Week 10, ending October 17th, 1998

Weekly progress summary:

  • Painting continues
  • Millwork and cabinet installation has begun
  • Suspended ceiling installation is in progress
  • Electrical and mechanical work nearing completion

Click on thumbnail image to see full-size version

98101701.jpg
98101701.jpg

24.24 Kb
98101702.jpg
98101702.jpg

20.74 Kb
98101703.jpg
98101703.jpg

23.29 Kb
98101704.jpg
98101704.jpg

23.69 Kb
98101705.jpg
98101705.jpg

18.38 Kb
98101706.jpg
98101706.jpg

21.89 Kb
98101707.jpg
98101707.jpg

24.19 Kb
98101708.jpg
98101708.jpg

16.97 Kb
98101709.jpg
98101709.jpg

15.45 Kb
98101710.jpg
98101710.jpg

15.23 Kb
98101711.jpg
98101711.jpg

12.03 Kb
98101712.jpg
98101712.jpg

11.21 Kb
98101713.jpg
98101713.jpg

15.41 Kb
98101714.jpg
98101714.jpg

15.73 Kb
98101715.jpg
98101715.jpg

13.30 Kb
98101716.jpg
98101716.jpg

16.78 Kb
98101717.jpg
98101717.jpg

19.85 Kb
98101718.jpg
98101718.jpg

23.24 Kb
planters.jpg
planters.jpg

(sample, off-site)

Home | Previous Week (9) | Next Week (11)


Prepared by
Larry O'Shaughnessy, architect

Comments are welcome !
mail.gif (14893 bytes)
lgoshaug@total.net

© 2014, Larry O'Shaughnessy architecte.
Date de la dernière mise à jour de cette page: 2014-10-31