Larry O'Shaughnessy architecte


 

MONTANK - NEW OFFICES, MONTREAL
5978 est, Notre-Dame, Montréal (Québec)

Construction Progress Report

These pages are dedicated to presenting a photographic report of construction progress of the above-mentioned project.

Week 12, ending October 31st, 1998

Weekly progress summary:

  • Painting completed.
  • Vinyl tile and carpet flooring completed.
  • Masonry veneer started - about 70% complete.
  • Metal siding started and about 80% complete.
  • Electrical and mechanical work essentially complete. (systems started and fuctioning explained to owner)

Following pictures actually taken on Tuesday October 27th, 1998
(not October 24th as labelled on picture)

Click on thumbnail image to see full-size version

98102401.jpg
98102401.jpg

20.73 Kb
98102402.jpg
98102402.jpg

23.34 Kb
98102403.jpg
98102403.jpg

22.04 Kb
98102404.jpg
98102404.jpg

21.68 Kb
98102405.jpg
98102405.jpg

22.50 Kb
98102406.jpg
98102406.jpg

23.51 Kb
98102407.jpg
98102407.jpg

21.60 Kb
98102409.jpg
98102409.jpg

16.88 Kb

Following pictures actually taken on Thursday October 29th, 1998

98102901.jpg
98102901.jpg

30.64 Kb
98102902.jpg
98102902.jpg

26.03 Kb
98102903.jpg
98102903.jpg

18.87 Kb
98102904.jpg
98102904.jpg

14.28 Kb
98102905.jpg
98102905.jpg

15.08 Kb
98102906.jpg
98102906.jpg

14.19 Kb
98102907.jpg
98102907.jpg

16.34 Kb
98102908.jpg
98102908.jpg

25.80 Kb

Home | Previous Week (10) | Next Week (12)


Prepared by
Larry O'Shaughnessy, architect

Comments are welcome !